On March 9, 2026, Fuquay-Varina's Town Board took up a request from Wilkes Asset Management for water and sewer capacity to serve Arbor Preserve. The request covered 119 residential lots and one commercial lot. Town staff recommended capacity for the first 75 residential lots and the commercial lot. The agenda abstract said the other 44 lots could apply only after the subdivision had certificates of occupancy on 60 lots.
The plant had room. The same memo showed 705,321 gallons per day of available treatment capacity at the Terrible Creek Wastewater Treatment Plant, and the recommended allocation used 31,100 of them. The request was trimmed because of a rule. The policy shapes how new subdivisions here fill in as plant capacity grows.
The rule that meters the pipe
Fuquay-Varina adopted its Water and Wastewater Utility Allocation Policy on November 16, 2021, by Resolution No. 21-1731. The minutes from that meeting describe water and wastewater capacity as finite and expensive to expand. They present the policy as a way to track and fairly distribute that capacity while treatment and conveyance infrastructure grows.
The policy and Town guidance describe allocation in phases:
- A developer submits an allocation request along with the preliminary subdivision plan or site plan. Under the Town's current guidance, those plans are not approved until the Board approves an allocation.
- Each phase is capped. The adopted policy sets the cap at 75 single-family, townhome or duplex lots, 18 triplex units, or 24 quadplex units.
- For a 75-lot phase, the policy ties a later allocation to certificates of occupancy on 60 lots.
- Under the 2021 text, an allocation can revert after 24 consecutive months without residential building starts.
The Town still applies the same approach. At an August 2026 meeting, Citizen Portal reported that engineering staff told the Board allocations happen at the preliminary subdivision stage. Staff described an initial 75-lot allocation, with later releases tied to build-out triggers.
Arbor Preserve, from master plan to first phase
Arbor Preserve shows how long that sequence takes before the cap even applies. The site is at 8537 Lake Wheeler Drive, at the northeast corner of Highway 540 and Lake Wheeler Drive.
| Date | Step |
|---|---|
| May 3, 2022 | Original Planned Unit Development master plan approved |
| February 2025 | Master plan revised |
| March 9, 2026 | Staff recommends utility allocation for 75 of 119 lots plus one commercial lot |
| Reported July 7, 2026 | Mungo Homes buys the roughly 35.3-acre tract for $4.75 million |
Hoodline reported that the 119 lots will be split among 60 townhomes, 25 row homes and 34 detached single-family houses, and that roughly 9.7 acres are set aside as open space. The Town's master-plan record lists TriPointe Homes as the earlier applicant.
Nearly four years passed between master-plan approval and the first allocation. The agenda abstract tied applications for the remaining 44 lots to certificates of occupancy on 60 lots. If you buy early in a community like this, ask about construction in later phases.
Capacity expansions and subdivision phases
A treatment plant at full capacity is the obvious thing that would limit growth, and Fuquay-Varina is about to add a lot of capacity. The Town's October 2026 newsletter says the Terrible Creek WWTP expansion, which began in fall 2024, will double capacity from 3 to 6 million gallons per day. It also adds processing tanks, filters, an expanded lab and a new administrative building for 24/7 operations, and completion is expected in February 2027.
The North Harnett Regional WWTP is growing as well, from 7.5 to 16.5 MGD. Under Harnett County's agreements with Fuquay-Varina, Angier and Lillington, Fuquay-Varina's share rises from 2.6 to 6.0 MGD, with completion estimated for early 2028.
Both dates are projections. The Arbor Preserve memo showed plenty of room at the plant when staff trimmed the request.
Woodcrest's 17-lot allocation request was approved on the May 19, 2026 consent agenda. Betts Farm Estates, with 13 lots, came before the Board on May 4, 2026.
Where a parcel ranks
The Town's January 20, 2026 policy excerpt is labeled as guidance that points to the official policy. It ranks service areas roughly in this order:
- Land inside town limits that existing gravity sewer and water lines already serve
- Land inside town limits that gravity lines could reach, first without a pump station, then with one
- Land in the extraterritorial jurisdiction that will be annexed and served by extending gravity lines
- Land outside the ETJ but inside the Urban Service Area that can be annexed and connected
The same document gives 70% of available capacity to residential use and 30% to nonresidential use. It also reserves up to 10% of the residential share for projects outside the Town's planning jurisdiction.
For buyers, the practical point is that a 27526 mailing address doesn't tell you where a property sits in this order. The October newsletter reminds residents that ZIP codes exist for mail delivery. The ETJ covers almost 26 square miles.
The projects working through the process now
The current Board calendar shows what will come up for allocation once Terrible Creek's added capacity is online.
Envision Homes has proposed Silva Preserves, 105 units on about 49 acres at 7151 Sunset Lake Road, just north of North Main Street and Bengal Towne Centre. The plan includes 64 single-family homes and 41 townhomes, and roughly 25 acres would stay open space with a public greenway. In a May meeting with neighbors, Curry Engineering Group's Andrew Petty estimated about 18 months to secure approval to break ground and another 12 to 18 months before any houses went up, the News & Observer reported. The rezoning was listed again on the Town Board's November 2 agenda as an item to be tabled further.
The same November 2 agenda included utility allocation requests for the Vaughn Park Mixed-Use Project and Sprouts Shopping Center. Madden West Subdivision appeared on the September 22 agenda for the same kind of request. An M/I Homes request for Planned Unit Development zoning on 27.63 acres at 6921 Sunset Lake Road was also listed as an item to be tabled on that September 22 agenda.
Roads and water service are following the same timeline. According to the September 8 Board minutes, the Town expected Sunset Lake Road Phase II widening to begin construction in early 2027 after right-of-way acquisition and final NCDOT review. Landmark Structures I, LP, holds the contract for the Wilbon Road Elevated Tank. The 1-million-gallon tank is scheduled to start construction in fall 2026 and finish by summer 2028 at an estimated $13,843,000, and western parts of town are expected to see water pressure rise by 10 to 20 PSI.
Questions this raises for a new-construction buyer
Which phase is this lot in, and how many of its lots have certificates of occupancy?
At Arbor Preserve, the agenda abstract tied applications for the remaining 44 lots to certificates of occupancy on 60 lots. If you would like a quiet street soon, ask the builder about the construction schedule. If you would like to see later phases open, so that more inventory and possibly new floor plans become available, ask about them too.
Has the next phase received its allocation?
The Board votes on allocation requests in public, and they appear on posted agendas and in posted minutes. Read those records alongside what the sales office tells you.
This post reports on Town policy as written and is general information, not legal, tax or financial advice. Please confirm how any rule applies to a specific property with the Town of Fuquay-Varina and the right professional.
If you are weighing a phase-one home in Fuquay-Varina against a resale in an established neighborhood, the timing of each project's phases is part of what you're comparing. Margaret Sophie follows these allocation votes and can help you see where a subdivision stands before you sign. Schedule a Consultation.